The NG-06R Semi-Automatic Mattress Rolling Machine is designed to help mattress manufacturers save space, reduce shipping costs, and improve overall packing efficiency. To ensure safe and optimal use, proper installation and correct operation are essential. This guide provides step-by-step instructions for setting up and operating the NG-06R, helping you get started quickly and avoid common issues.


1. Unpacking and Pre-Installation Checklist

Before installation, follow these steps:

  • Inspect Equipment: Check the machine and components for damage during transport. Contact NAIGU immediately if any issues are found.

  • Choose a Suitable Location: Ensure the installation area is clean, level, and has enough space for the operator to work around the machine safely.

  • Electrical Requirements: The NG-06R requires a stable 3-phase power supply (customizable voltage). Ensure correct wiring and grounding by a certified electrician.

  • Air Supply: Connect to a stable compressed air source. Recommended pressure: 0.6–0.8 MPa.


2. Installation Steps

  • Step 1: Position the Machine
    Place the NG-06R in the desired working area. Use a level to ensure stability.

  • Step 2: Connect Air and Power
    Attach the air hose securely and connect the machine to the power supply.

  • Step 3: System Check
    Turn on the main power. Ensure emergency stop is released. Check that the control panel and touch screen (if equipped) are responding correctly.

  • Step 4: Trial Run
    Run the machine without a mattress to ensure the compression rollers and belts move correctly.


3. Operation Guide

Step-by-Step Use:

  • Step 1: Place the Mattress
    Put the mattress (foam or spring type) on the feeding conveyor. Align it properly for centered compression.

  • Step 2: Adjust Parameters
    Set the rolling direction, compression level, and film feeding mode via the control panel or button interface.

  • Step 3: Start Compression
    Press the “Start” button. The machine will compress and roll the mattress while feeding it into the packing film.

  • Step 4: Film Cutting (Manual/Auto)
    Depending on configuration, the operator may manually cut the film or let the auto-cut system complete the task.

  • Step 5: Discharge
    Remove the rolled mattress from the output end. The product is now ready for shipping or storage.


4. Safety Tips

  • Always keep hands and loose clothing away from moving parts.

  • Use emergency stop in case of abnormal noise or movement.

  • Do not open the electrical cabinet without authorization.

  • Only trained personnel should operate or maintain the machine.


5. Maintenance Reminders

  • Clean dust and fabric residues daily.

  • Lubricate moving parts weekly.

  • Inspect air tubes and belts monthly.

  • Replace any worn components as needed to avoid unexpected downtime.


Conclusion

Proper installation and operation of the NG-06R mattress rolling machine ensures smooth production and longer machine lifespan. With semi-automatic functionality, it strikes the perfect balance between cost-effectiveness and operational efficiency—making it ideal for growing mattress factories.

Need Technical Assistance or Installation Support?
NAIGU offers full technical guidance and after-sales service for the NG-06R Mattress Rolling Machine. Whether you need remote setup support, spare parts, or user training, our team is here to help.

📧 Email: jenney@gdnaimei.com
📱 WhatsApp/Phone: +86 13924835577
🌐 Website: https://naigumattressmachine.com

We're ready to support your production line—anytime, anywhere.

Need Help Choosing the Right Machine ?
Full Name :
Your Email :*
WhatsApp/Phone:
Message:*
Verification Code:*
Verification Code